SAP Knowledge Base Article - Public

1236390 - Error Message 'Enter a Valid Unit of Measurement' Occurs When Posting a Manual Adjustment to a Time Account

Symptom

When you are entering the adjustment for a vacation time account, an error occurs: 'Enter a valid unit of measurement'.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Time Administration work center.
  2. Go to Employees view.
  3. Select the relevant employee and click Edit button.
  4. Go to Time Account Balances tab.
  5. Select the Time Account and select sub-tab Adjustments.
  6. Click Add Row button and fill in the details.
  7. Click Save button.

The error 'Enter a valid unit of measurement' may appear.

Cause

The related Unit of Measure (DAY for example) is in status Blocked and needs to be activated in the Business Configuration.

Resolution

  1. Go to Business Configuration work center.
  2. Go to Implementation Projects view.
  3. Select the current project and click Open Activity List button.
  4. Go to Fine-Tune tab.
  5. Search for activity Quantities and Units of Measure and select the link to open it.
  6. Select link Create and Maintain Physical Units.
  7. Select the relevant unit of measure and change the status from Blocked to Released.
  8. Click Save and Close button.