Symptom
Your requirement is to create a Working Day Calendar for a non-localized or pre-localized Country, but the respective non-localized Country XYZ is not available under the List of Countries in the Working Day Calendar activity (where XYZ represents the country name).
Environment
SAP Business ByDesign
Reproducing the Issue
-
Go to Business Configuration work center.
-
Enter the Implementation Projects view.
-
Select the implementation project.
- Click on the Open Activity List button.
-
Search for the activity Working Day Calendar.
- Click on the name of the activity name to open it.
-
Click on Create new working day calendar.
The required non-localized country is missing in the list of countries available.
Resolution
Working Day Calendar for non-localized and pre-localized Countries is currently not available in the project scope.
In these scenarios, it is possible to create a calendar while selecting a different country, and still assign it to the required organization unit.
To create a New Holiday Calendar, please follow the steps below:
- Go to Business Configuration work center.
- Enter the Implementation Projects view.
- Select the implementation project.
- Click on the Open Activity List button.
- Search for the activity Working Day Calendar.
- Click on the activity name to open it.
- Click on Create New Holiday Calendar.
- Select a different country available from the list.
- Proceed in the wizard to create the holiday calendar.
Note: For country-specific holidays which are not available, it is possible to create a new holiday by clicking on the Add Row button in the holiday selection step.
After creating the New Holiday Calendar, it is required to assign it to a working day calendar. In order to create a working day calendar, please follow the below steps:
- Go to Business Configuration work center.
- Enter the Implementation Projects view.
- Select the implementation project.
- Click on the Open Activity List button.
- Search for the activity Working Day Calendar.
- Click on the activity name to open it.
- Click on Create New Working Day Calendars
- Choose the same country for which the holiday calendar was created.
- Select the Country XYZ for which the New Holiday Calendar was created previously
- Proceed with the wizard, and assign the holiday calendar created to it.