SAP Knowledge Base Article - Public

1552527 - Error Message: "Cost center XYZ (Cost center name)/set of bks (Set of bks name); At least 1 period total unequal 0 in DD/MM/YYYY-DD/MM/YYYY"

Symptom

You as a Organizational Manager, When you try to delimit a particular org unit. System throws below error message:

Cost center XYZ (Cost center name)/set of bks (Set of bks name); At least 1 period total unequal 0 in DD/MM/YYYY-DD/MM/YYYY

Reproducing the Issue

  1. Go to Organizational Management work center.
  2. Select Edit Org Structures.
  3. Highlight an Org unit.
  4. Go to Definitions tab.
  5. Uncheck the cost center attribute.

Cause

The system works as designed.

Resolution

If there are postings to the cost centers XYZ, then it is not possible to delimit these cost centers. The cost centers must remain valid until the end of the accounting period due to possible period closing postings in this period.

Keywords

KBA , AP-PRO , Project Processing , Product Enhancement

Product

SAP Business ByDesign all versions