1626525 - New planned orders are created if requirement date is changed

Symptom

A planned order was generated by MRP to cover a given requirement, and:

  • If the requirement date is moved to another date in the future, the same planned order (if not firmed) is also moved in the future to cover the requirement by the next MRP run.
  • If the requirement date is moved to a date in the past, a new planned order is created by MRP to cover the requirement even if planning mode 1 is used.


Read more...

Environment

  • SAP ERP Release Independent
  • Material Requirements Planning - PP-MRP

Keywords

planned order, delete table, reuse, MRP, planning mode 1, MD01, MD02, MD03 , KBA , PP-MRP , Material Requirements Planning , MM-CBP-CBP , Consumption-Based Planning (see also PP-MRP) , Problem