Symptom

  • On the Progress tab of a project object, for example, WBS Element or Network Activity, you enter data for Method Plan and Method Actual.
  • The Plan Default and Actual Default field texts are swapped around.


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

EVVS, EVMET_ACT2PLN, EVMET_PLN2ACT, EVOPD-EVMET_TXT_P, EVOPD-EVMET_TXT_A , KBA , PS-PRG , Progress , How To

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.