Symptom

Cannot edit the activities in Fine Tuning as there is no Implementation projects found in Business Configuration.

Reproducing the Issue

  1. Go to Business Configuration Work Center
  2. Select view Implementation Projects

There will be no Implementation projects available to edit the activities in Fine Tuning

Cause

Go-Live activity has been completed for the First Implementation project.

Resolution

You can edit the activity by Change Immediately or Add To New Change Project:

  1. Go to Business Configuration Work Center
  2. Go to Overview
  3. Find the desired activity which you need to edit
  4. Highlight the activity;
    • If the button Change Immediately is active, you can edit the activity by pressing the button
    • If the activity cannot be edited by Change Immediately, you can create a new change project by clicking on the button Add To New Change Project