Symptom
Planned orders have been split by MRP correspondent takt time. If you convert these planned orders to production orders the exception messages '15' or '10' is raised for the production orders in transaction MD04.
The rescheduling check doesn't consider the takt time.
Read more...
Environment
SAP Release independent
Product
SAP ERP Central Component all versions ; SAP R/3 4.6C ; SAP R/3 Enterprise all versions ; SAP enhancement package for SAP ERP all versions
Keywords
MARC-TAKZT , KBA , PP-MRP , Material Requirements Planning , How To