Symptom
Your requirement is to Edit/Add an activity in a Merged Change Project, but system throws message:
Settings cannot be changed
Reproducing the Issue
- Go to Business Configuration work center
- Highlight your Merged Change Project, and select Open Activity List button
- Select the activity
OR
- Go to Business Configuration work center
- Highlight your Merged Change Project, and select Open Activity List button
- Select the activity
- Select Add to Project button
Cause
Once the Change Project has been Merged no change can be done on this project. Only Confirm Go-live and Close Project activities are Open.
Resolution
If Change Immediately button is available for the activity, you may change the activity using the below steps:
- Go to Business Configuration work center
- Go to Overview view
- Search for the activity
- Select Change Immediately button and make the desired changes
If the Change Immediately button is not available for the activity, a new Change Project will be required or in case you already have a Change Project with status Started, you can Add this activity to the Change Project and make the desired changes.