Symptom
You find a lot of manually selected activities disappear from activity list.
Reproducing the Issue
1 Go to WoC: Business Configuration
2 Go to View: Implementation Projects
3 Select the project
4 Click Open Activity List
5 Go to Fine Tunning
6 You find some activities disappear and some activities change status.
Cause
The issue will happen if the following steps are performed:
- You have already added activities in the activity list.
- You open the scoping and click Save Draft.
- You close the scoping without finish.
- You open the scoping again and click Finish.
Step 3 will lead to the loss or status change of manually selected activities. It should be avoided in operation.
Resolution
Re-add the activities to activity list.
Keywords
KBA , AP-RC-ANA , C4C, ByD, Travel: Analytics Tools & Frameworks , Product Enhancement
Product
SAP Business ByDesign all versions