SAP Knowledge Base Article - Public

1705462 - Status and Life Cycle of Implementation/Change Projects at Different Stages

Symptom

The Implementation Project's status has changed at different stages.

Environment

  • SAP Business ByDesign
  • SAP Cloud for Customer

Reproducing the Issue

  1. Go to the Business Configuration work center.
  2. Go to the Implementation Projects view.
  3. In column Status, the current status of the Implementation Project will be displayed.

Resolution

The following are the different status that can be observed on a Implementation Project's Life Cycle.

RemarkStatus
  • Initial status of the implementation project
In Preparation
  • Confirming the milestone Scoping Completed
Started
  • Confirming the milestone Test Completed
Tested
  • Closing the activity Merge Changes with Production System
Merged
  • Closing the activity Activate Solution Capabilities
Activated
  • Confirming the milestone Go Live
Completed
  • Confirming the milestone Close Project
Closed

Keywords

change project, status, started, tested, activated, merged, life cycle, different stages , KBA , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To

Product

SAP Business ByDesign all versions ; SAP Cloud for Customer add-ins all versions ; SAP Cloud for Customer core applications all versions