Symptom
You find implementation project's status is changed at different stages.
Environment
- SAP Business ByDesign
- SAP Cloud for Customer
Reproducing the Issue
- Go to the Business Configuration work center.
- Go to the Implementation Projects view.
- In column Status, you can see different status of implementation projects.
Resolution
Initial status of the implementation project is In Preparation.
Confirming the milestone Scoping Completed changes the status of the project to Started.
Confirming the milestone Test Completed changes the status of the project to Tested.
Closing the activity Merge Changes with Production System changes the status of the project to Merged.
Closing the activity Activate Solution Capabilities changes the status of the project to Activated.
Confirming the milestone Go Live changes the status of the project to Completed.
Confirming the milestone Close Project changes the status of the project to Closed.