Symptom
-
Error CJ009 - Start date must be later than "01.01.1980" happens when you create a project with a start date which begin before 01.01.1980.
-
Error CJ012 - Finish date must be earlier than "19.01.2048" occurs if you put finish date after than 19.01.2048 while creating a project.
- Short dump MESSAGE_TYPE_X occurs when removing status TECO for a network activity in transaction code CJ20N.
Message class....... "C7"
Number.............. 133
This dump could also occur in other cases if you maintained a date for a project or a network which is not in the time frame from 01.01.1980 to 19.01.2048.
Read more...
Environment
- SAP ERP Project System (PS)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
CJ 009, CJ 012, C7133, CJ 133, WBS delete, SAPLCXTK, CX_OPR_SCHEDULE, SAPLCNPB_M, network activity, nwa , KBA , PS-ST-PB , Project Builder , PP-CRP-SCH , Scheduling , PP-CRP , Capacity Planning , Problem