Symptom
You cannot edit the scope of a change project once it is in the status Merged.
Reproducing the Issue
- Go to Business Configuration Work Center.
- Go to Implementation Projects View.
- In field Show, choose option All Projects.
- Select a project with status Merged.
You can see a View Project Scope instead of Edit Project Scope which leads to a read only view of project scope.
Cause
The changes in the scoping carried out through the change project have already been merged with the production system. So, it is not possible to change the scope of a Merged change project.
Resolution
You can include the changes in any existing change project or create a new change project to include the desired scoping changes.
Keywords
KBA , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To
Product
SAP BUSINESS BYDESIGN 1611 ; SAP BUSINESS BYDESIGN 1705 ; SAP BUSINESS BYDESIGN 1708 ; SAP Business ByDesign 1411 ; SAP Business ByDesign 1502 ; SAP Business ByDesign 1505 ; SAP Business ByDesign 1508 ; SAP Business ByDesign 1511 ; SAP Business ByDesign 1602 ; SAP Business ByDesign 1605 ; SAP Business ByDesign 1608 ; SAP Business ByDesign 1702