SAP Knowledge Base Article - Public

1792326 - Error Message "Please close all the activities before merge back"

Symptom

When you open the Merge Changes with Production System activity, system throws below error message:

Please close all the activities before merge back

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Business Configuration work center.
  2. Select the Implementation Projects view.
  3. Highlight the Change Project and select the Open Activity List button.
  4. Go to Go Live phase.
  5. Highlight the Merge Changes with Production System activity and select the Open button.

Cause

The cause for the issue is that you have not closed some activities in Prepare, Fine-Tune, Integrate and Extend, and Test phase of the Change Project. So, ensure that you have closed all the activities in all the phases of Change project.

Resolution

Once you have closed all the Activities, go to the Go Live phase in the change Project. Open the activity Merge Changes with Production System and select the Start Merge button.

Note: Once the Merge is successful, the status of the change project will change to Merged.

Keywords

KBA , please close all the activities , merge changes , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To

Product

SAP Business ByDesign all versions