Symptom
When you try to confirm the activity Go-Live Readiness Accepted, the check box is geryed out.
Cause
you cannot confirm the milestone, if you have requested a new production/test system.
Resolution
You have to confirm the Milestone: Go-Live Readiness Accepted in the new system which you have requested.
Keywords
KBA , greyed out , go-live readiness accepted , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , Product Enhancement