SAP Knowledge Base Article - Public

1794959 - Unable to Confirm Milestone: Go-Live Readiness Accepted, Since the Check Box is Greyed Out

Symptom

When you try to confirm the activity Go-Live Readiness Accepted, the check box is geryed out.

Cause

you cannot confirm the milestone, if you have requested a new production/test system.

Resolution

You have to confirm the Milestone: Go-Live Readiness Accepted in the new system which you have requested.

Keywords

KBA , greyed out , go-live readiness accepted , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , Product Enhancement

Product

SAP Business ByDesign all versions