Symptom
"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."
How to revert the status of a Implementation Project or a Change Project from status Tested to Started?
Environment
- SAP Business ByDesign
- SAP Cloud for Customer
Resolution
- In order to revert the Project status from Tested to Started, please follow the below steps:
- Go to Business Configuration work center.
- Select Implementation Projects view.
- Highlight Implementation Project or Change Project and select Open Activity List button.
- Go to Test phase.
- Highlight Confirm Milestone: Go-Live Readiness Acceptance activity and select Open button.
- Uncheck Go-Live Readiness Accepted check box.
- Select Confirm button.
- Now, you can find that the status of the Implementation Project or Change Project reverted to Started.
See Also
You can also rever the KBA: 1922087 - How to Create a Change Project and Its Lifecycle
Keywords
Tested, Started, Go-Live Readiness Acceptance activity, Go-Live, Readiness Acceptance activity. , KBA , go-live, readiness acceptance activity. , tested, started , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To
Product
SAP Business ByDesign all versions ; SAP Cloud for Customer add-ins all versions