Symptom
When you select an Implementation project or a Change Project, system shows This project is active only in the test system. Open the test system to continue working on the project at the bottom of the screen.
Reproducing the Issue
- Go to Business Configuration work center.
- Select Implementation Projects view.
- Highlight the Implementation Projects or Change project.
Cause
The reason for this information is that, you have requested a Test System for the selected Change Project or Implementation Project. If this is a case, you can also find the System Status of this Project as Test System Available.
Resolution
This is general system behavior.
Hence, any changes to this Project should be performed in the respective Test System. Once, the changes are completed then perform the Merge from the Test system to the Productive.
Note: After the merge, you can able to work in the Project in Productive system only for the activities which has Repetition Required.