1888472 - What is the report E2E_EFWK_RESOURCE_MGR used for?

Symptom

What is the report E2E_EFWK_RESOURCE_MGR used for?

Environment

Solution Manager 7.1

Reproducing the Issue

The report E2E_EFWK_RESOURCE_MGR can be resource intensive, what is it used for?

Cause

N\A

Resolution

E2E_EFWK_RESOURCE_MGR report (job EFWK RESOURCE MANAGER): This job is checking if data extractors defined within the EFWK in table E2E_ACTIVE_WLI are due to execution regarding their actual status described in table E2E_EFWK_STATUS. If data extractors are due, then they are executed in the managed systems via RFC calls due to the settings in the table E2E_RESOURCES.If no extractors are due, the report is finished immediately, generating no further workload. By default the job is scheduled every minute. Since ST710 SP1.