Symptom
- The order's basic dates do not align with the factory calendar assigned to the work center.
- The production start date or finish date for the order falls on a non-working day according to the factory calendar.
“Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.”
Read more...
Environment
- SAP ERP Capacity Planning (PP-CRP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 all versions ; SAP S/4HANA all versions
Keywords
CO01, CO02, CO03, MD11, MD12, MD13, capacity, production order, planned order, process order, scheduling, basic dates, production dates, non-working day, working day, SCAL, duration , KBA , PP-CRP-SCH , Scheduling , PP-PI-POR , Process Order , PP-SFC , Production Orders , PP-MRP , Material Requirements Planning , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.
SAP Knowledge Base Article - Preview