1902072 - Project Expense and Revenue Planning using Microsoft Excel® - Known Issues

Symptom

1. In the excel, there can be only 8 project task hierarchy levels. All the tasks in hierarchy after the 8th level will be displayed at the 8th level itself.

2. Filtering and sorting in the excel does not ensure data consistency. User is advised not to use those functionalities.

3. Selecting multiple rows, and using the copy/cut and paste function is not advised as it will result in data inconsistency.

4. Translation of the excel worksheet name will always be in English and it should not be changed.

5. Row grouping is not ensured if Microsoft Excel® provided insert is used.

6. Expense Group and Income Group drop downs will always display all the values irrespective of the group.

7. In the Cost and Revenue -> Projects OWL -> advanced search -> Project Type, provide multiple values (Customer project with Sales Integration, Direct cost project). when you download the excel, only one project type will be present in the downloaded excel.