Symptom

Following phenomena may occur on SLT replication.

  • You started a replication in Data provisioning of HANA Studio, but the replication remained in status "Scheduled".
  • Some tables were update on source system, but the new data were not synchronized to HANA system.
  • You saw long latency time in tag page Statistics of Configuration in the Configuration & Monitoring Dashboard.


Read more...

Environment

  • DMIS 2010 all SPs
  • DMIS 2011 all SPs

Product

SAP Landscape Transformation replication server 1.0 ; SAP Landscape Transformation replication server 2.0

Keywords

SLT, Replication not work, Table not generated, Transfer job, Calculation job, Background Processes, LTRC, LTR, Replication Schema, SLT configuration , KBA , HAN-DP-LTR , Use CA-LT-SLT instead , How To