Symptom
On the customizing scheduling parameters for planned orders you have chosen "forward scheduling" and also the option "adjust basic dates".
For a planned order created by MRP, you observe the following symptoms:
- MRP considers the requirement date as basic finish date and calculates the basis start date using backward scheduling
- The planned order basic finish date is equal to the requirement date and it is not adjusted according to the production finish date.
Read more...
Environment
- SAP ERP Production Planning (PP)
- SAP ERP
- SAP ERP Central Component
- SAP Enhancement package for SAP ERP
- SAP S/4HANA, on-premise Environment
- SAP Fiori for SAP ERP
- SAP Fiori for SAP S/4HANA
- SAP Fiori for SAP S/4HANA Cloud Private Edition
- SAP S/4HANA Cloud Private Edition
Product
Keywords
scheduling, backwards, forwards, MRP, material requirements planning, MD01, MD02, MD03, MDBT, MD40, MD41, MD42, MDBS, MS01, MS02, MS03, MSBT, MD11, MD12, MD13, MD04, MD05, stock/requirements list, MRP list, OPU5, basic finish date, PEDTR, PSTTR, GLTRS, GSTRS, PLAF. , KBA , PP-MRP , Material Requirements Planning , PP-CRP-SCH , Scheduling , Problem