1913017 - MRP: Forward scheduling and adjust basic dates

Symptom

On the customizing scheduling parameters for planned orders you have chosen "forward scheduling" and also the option "adjust basic dates".

For a planned order created by MRP, you observe the following symptoms:

  • MRP considers the requirement date as basic finish date and calculates the basis start date using backward scheduling
  • The planned order basic finish date is equal to the requirement date and it is not adjusted according to the production finish date.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP ERP
  • SAP ERP Central Component
  • SAP Enhancement package for SAP ERP
  • SAP S/4HANA, on-premise Environment
  • SAP Fiori for SAP ERP
  • SAP Fiori for SAP S/4HANA
  • SAP Fiori for SAP S/4HANA Cloud Private Edition
  • SAP S/4HANA Cloud Private Edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP Fiori for SAP ERP all versions ; SAP Fiori for SAP S/4HANA Cloud Private Edition all versions ; SAP Fiori for SAP S/4HANA all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions

Keywords

scheduling, backwards, forwards, MRP, material requirements planning, MD01, MD02, MD03, MDBT, MD40, MD41, MD42, MDBS, MS01, MS02, MS03, MSBT, MD11, MD12, MD13, MD04, MD05, stock/requirements list, MRP list, OPU5, basic finish date, PEDTR, PSTTR, GLTRS, GSTRS, PLAF. , KBA , PP-MRP , Material Requirements Planning , PP-CRP-SCH , Scheduling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.