Symptom
Changes made in the scoping or fine-tuning activities of the Business Configuration work center, however those changes are not reflecting in your system.
Environment
- SAP Cloud for Customer
- SAP Business ByDesign
Cause
The cause for the issue could be that changed project is not merged.
Resolution
If the changes are being done through a change project, then it is always mandatory to merge the change project in order to reflect the changes into the system.
Final status of the change project should be Merged (or Activated, in cases where the Activate Solution Capabilities activity is available, as it must be completed after the merge). Repetition Required activities should also be re-configured after merge.
See Also
Keywords
Changes, Not Reflecting, System, Business Configuration, Fine-Tuning, Activities, Change Project , KBA , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To