Symptom
Exception message 10 is not displayed though all settings required are in places, here is an example.
A requirement of reservation exists at 21.12.2013 prior to a firmed planned order at 23.12.2013, so there should be an exception mesage 10 in the planned order to show that it can be rescheduled in to meet the requirement, but it doesn't happen.
The customization for rescheduling in is configured correctly as following.
The rescheduling horizon is long enough to cover the firmed planned order and firmed planned order is allowed to participate rescheduling in, also, there are no tolerance values, so the exception message should appear generally.
Read more...
Environment
- SAP ERP Production Planning (PP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
Keywords
KBA , PP-MRP-PE , Planning Evaluation , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.
SAP Knowledge Base Article - Preview