1957695 - Purchase Requisitions are created too far into the future

Symptom

  • You create a Purchase Requisition at the Product View or convert an SNP PurRqs into PP/DS PurRqs
  • The order is scheduled too late, with availability date after the end of the time stream of the Transportation Resource


Read more...

Environment

  • SAP Supply Chain Management (SCM)
  • SAP Advanced Planning and Optimization (SCM-APO)
  • SAP enhancement package for SAP Supply Chain Management
  • SAP enhancement package for SAP SCM, version for SAP HANA
  • SAP Supply Chain Managment Production Planning and Detailed Scheduling (SCM-APO-PPS)
  • External Procurement Planning in SCM APO PP/DS

Product

SAP Supply Chain Management 2005 ; SAP Supply Chain Management 2007 ; SAP Supply Chain Management 4.0 ; SAP Supply Chain Management 4.1 ; SAP Supply Chain Management 7.0 ; SAP enhancement package 1 for SAP Supply Chain Management 7.0 ; SAP enhancement package 2 for SAP Supply Chain Management 7.0 ; SAP enhancement package 3 for SAP Supply Chain Management 7.0 ; SAP enhancement package 4 for SAP Supply Chain Management 7.0

Keywords

PP/DS Horizon, Days Plus, Days+, Transportation Resource, OVERLAP_BUCKETS, /SAPAPO/CRES_OVERLAP_BUCKETS, External Procurement, STO, Stock Transport Orders, Stock Transfer Orders , KBA , product view , /sapapo/res01 , purchase requisition created farther , preq does not respect pdt , preq scheduled too late , preq created too far , scheduled too late , sapapo/rrp3 , converting snp orders so longer , conveting snp orders too far , SCM-APO-PPS , Production Planning and Detailed Scheduling , SCM-APO-INT-PUR , Purchasing / Purch. Req. and Order, Transfer Order , SCM-APO-MD-RE , Resource , Problem