1966063 - Project Baseline didn't go for Approval Process

Symptom

Project Baseline didn't go for approval process though it is submitted for approval.

Environment

SAP Business Bydesign

Reproducing the Issue

  1. Go to Project Management work center.
  2. Go to Change Management view.
  3. Search for the relevant project ID.
  4. Select the relevant baseline ID. 
  5. Click in View button. 

Confirm that the Baseline status is Active. It was expected "In Approval" status instead. 

Note: when the Baseline is created, its status is Active. If the Baseline is send back to revision, its status is In Planning. 

Cause

The Approval Process for Project Baseline is not scoped. 

Resolution

The steps below show how to configure the Project Baseline Approval process: 

  1. Go to Business Configuration work center.
  2. Go to Implementation Projects view.
  3. Select the relevant implementation project.
  4. Click in Edit Project Scope button.
  5. Navigate to Questions.
  6. Under Scoping Element, select "Project Management" and select "Choose Change Management". 
  7. Check the question "Do you want to use an approval process for project baseline?" for normal approval process; check the question "Do you want to use a multi-step approval process for project baselines?" for multi-step approval process. 
  8. Click Next and Finish Scoping.

Note: If the multi-step process is scoped, then only consider the "Application and User Management work center - Approvals Process view". 

Keywords

Project baseline, Baseline approval , KBA , AP-PRO , Project Processing , How To