SAP Knowledge Base Article - Public

1970348 - Unable to find Project Baseline Approval Tasks and Project Purchase Request Approval Tasks.

Symptom

In the Approvals view the value search help for the Project Baseline Approval Tasks and Project Purchase Request Approval Tasks are not available to Approve the Project Baseline and Project Purchase Request.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Managing My Area work center.
  2. Choose Approvals view.
  3. Under Show value search help Project Baseline Approval Tasks and Project Purchase Request Approval Tasks are not avilable.

Cause

The Work Center / View ID MMA_MYPROJECTS - My Projects is not assigned to User.

Resolution

To resolve this issue follow below steps.

  1. Go to Application and User Management work center.
  2. Choose User and Access Management view.
  3. Choose Business Users subview.
  4. Choose the Business Users for whom this Project Baseline Approval Tasks and Project Purchase Request Approval Tasks are not available.
  5. Choose Edit --> Access Rights button.
  6. Choose MMA_MANAGINGMYAREA expand .
  7. Choose MMA_MYPROJECTS enabke the check box.

Once the Work Center / View ID MMA_MYPROJECTS - My Projects for the User he will be able to see Project Baseline Approval Tasks and Project Purchase Request Approval Tasks under Show value help of Approval View --> Managing My Area work center.

Keywords

KBA , AP-PRO , Project Processing , How To

Product

SAP Business ByDesign all versions