Symptom

You have created production request but you are not able to see any Requested Input Products in the created Production Request XXX (XXX represents the Production Request ID).

Reproducing the Issue

  1. Go to Production Control work center.
  2. Navigate to Production Request view.
  3. Edit the Production Request XXX.
  4. Navigate to Production Segments page.
  5. Navigate to Details sub-view.
  6. Choose Input Products tab.

You see that requested input products is empty.

Cause

Since the Explosion Date of your Production Request XXX is prior to the Input Materials Valid From Date of your Production Bill of Materials (BoM): XYZ (XYZ represents the BoM ID), the system does not show these Input Materials.

Example :

The Explosion date in your Production Request XXX is 28.12.2017.

You have a Production BoM: XYZ with Input Products Valid From 01.01.2018.

Since the Explosion Date of your Production Request XXX is on 28.12.2017 when compared to the Input Materials Valid From 01.01.2018 of your Production BoM: XYZ, the system does not consider these Input Materials.

Resolution

This is the standard system behavior and the system is working as designed.