Symptom
You want to close or set deletion flag in the project and receive message KO 115.
The project is carrying costs and you want to prevent users from closing the project or setting deletion flag.
Relevant system message: KO 115
The balance on object is not zero. That is, there are still costs on the object.
Read more...
Environment
release independent
Product
Keywords
TAGB LOEVM LÖVM Oligo Abrechnungsprofil KO115 KO 115 Projektdefinition PSP-Element Netzplanvorgang Vorgang Istkosten
TECO DLFL commitment settlement profil projectdefinition WBS element network activity order actual costs actuals , KBA , changing system status , PS , Project System , How To