2001359 - Project and Project Task are Shown as Not assigned in the Cost Centers - Line Items Report

Symptom

In the Report Cost Centers - Line Items, Project and Project Task are shown as #, which means Not Assigned.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the work center Cost and Revenue.
  2. Go to the view Reports.
  3. Select the report Cost Centers - Line Items.
  4. Specify the Cost Center and other necessary data.
  5. Click the button OK to display the report.

 You can see for each line item, the Project, and Project Task are shown as Not Assigned.

Cause

When you check the Cost Center - Line Items report for the desired selection criteria, in the result list, you can, for example, see a list of transaction types being Internal Service Confirmation. A time confirmation credits cost center of the employee and debits the project task. Your G/L Account labor overhead reflects the credit postings for the employee costs. The project task information and the related project details are only visible via the offset characteristics.

Resolution

To see the project task information for each relevant item, follow the steps below:

  1. Go to the work center Cost and Revenue.
  2. Go to the view Reports.
  3. Select the report Cost Centers - Line Items.
  4. Specify the Cost Center and other necessary data.
  5. Click the button OK to display the report.
  6. Go to the Not Currently Shown, and find Offset Project Task, and move it to row.

After that, you should be able to see the related project task information.

Keywords

Project, Project Task, Cost Centers-Line Items, Not Assigned. , KBA , not assigned , project task , cost centers-line items , SRD-FIN-GL , General Ledger , How To