When displaying the itemization of a cost estimate in t-code CK11N, CK13N etc. the value of an internal activity does not match the calculation
Value = Time * Price
Instead the value seems to be rounded.
Example:
The activity price is 60 EUR per Hour and the quantity is 5 minutes. So, the expected result is 5 EUR, but system displays 4,98 EUR.
Read more...
Environment
- Controlling (CO)
- SAP R/3
- SAP R/3 Enterprise 4.7
- SAP ERP Central Component
- SAP ERP
- SAP enhancement package for SAP ERP
- SAP enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA
- SAP S/4HANA Finance
Product
Keywords
CK11N, CK13N, CK40N, product costing, cost planning, UoM, Unit of Measure, internal, line item, itemization, operation duration, type, standard cost estimate, lot size, hours, minutes, rounded, rounding, slight differences, decimals decimal, hourly rate, cost center , KBA , inforecord , info record , CO-PC-PCP-WQS , Product Costing with Quantity Structure , CO-PC-PCP , Product Cost Planning , Problem