SAP Knowledge Base Article - Public

2048173 - How To Update a Change Project from Productive System

Symptom

After doing immediate changes in the active workspace of your productive tenant after creating a change project, it is necessary to update the open change project with the data that has been changed to avoid inconsistences during merge back. This knowledge base article explains how to execute this operation.

Environment

  • SAP Cloud for Customer
  • SAP Business ByDesign

Resolution

  1. Go to Business Configuration work center.
  2. Access the Implementation Project work center view.
  3. Click the link in the relevant change project's title.
  4. In the new screen, click the Actions button.
  5. Select option Update Project from Production option.
  6. After the update is done, the change project should be consistent with the productive system.

Note: in case of a remote change project, these steps must be executed in the test tenant to which the change project was moved.