2070724 - The Project Finish Date Not Auto Calculated for Migrated Projects.

Symptom

The Projects Finish Date was not calculated automatically or it is incorrect  for migrated project. However the duration for project task was set.

Reproducing the Issue

  1. Go to Project Management work center
  2. Select the Projects view
  3. Select the Projects subview 
  4. Search for the Project ID XYZ
  5. Edit the project
  6. Go to Project plan tab, select the project header you see that the Start date and Finish date are same . However the project duration n days maintained.

Cause

The projects that are migrated with the released status may have incorrect Finish Date however you see that the duration is set. Based on the Start date and duration the Finish date will not automatically get adjusted. Once a project is in the released status, the scheduling requires the manager to manually Schedule the project to see the adjusted dates and duration. If the dates and duration are required to be automatically calculated, then the project has to be In planning. However, this would again mean that there is a manual release that the project manager is expected to do for every project.

Resolution

The system is working as designed.

Keywords

KBA , AP-PRO , Project Processing , How To

Product

SAP BUSINESS BYDESIGN 1611 ; SAP BUSINESS BYDESIGN 1705 ; SAP BUSINESS BYDESIGN 1708 ; SAP Business ByDesign 1402 ; SAP Business ByDesign 1405 ; SAP Business ByDesign 1408 ; SAP Business ByDesign 1411 ; SAP Business ByDesign 1502 ; SAP Business ByDesign 1505 ; SAP Business ByDesign 1508 ; SAP Business ByDesign 1511 ; SAP Business ByDesign 1602 ; SAP Business ByDesign 1605 ; SAP Business ByDesign 1608 ; SAP Business ByDesign 1702 ; SAP Business ByDesign 1711