Symptom
After creating the base cost for the various resources (Instructor, Location, Equipment, Materials, Facilities, Custom Resources) at Learning > Resources, how does one ensure that the base cost will be transferred to the Scheduled Offering
Environment
SAP SuccessFactors Learning Management System (LMS) - All Supported Versions
Resolution
After entering the amount, currencies, and/or unit of measure, click Apply Changes.
At the bottom of the screen, ensure to click Propagate which will bring up the next screen. This provides three options to apply the base cost to Scheduled Offering that will use that resource.
Without propagation, there is no association of this base cost to any Scheduled Offering.