Symptom
In the Project Variance by Project Structure Report we can't see the Baseline Cost for some of the Baselines.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Business Analytics Work Center.
- Navigate to the Reports view and click on List sub View.
- Choose all reports in Show field and filter with Project Variance by Project Structure in the Find field.
- Open the Project Variance by Project Structure in web browser.
- Pull the Project, Project Task, Baseline in Row.
- Choose Go button.
- Here you will be able to see the for some baseline the baseline cost is not shown.
Or
- Go to the Project Management Work Center.
- Navigate to the Reports view and click on List sub view.
- Choose all reports in Show field and filter with Project Variance by Project Structure in the Find field.
- Open the Project Variance by Project Structure in web browser.
- Pull the Project, Project Task, Baseline in Row.
- Choose Go button.
- Here you will be able to see the for some baseline the baseline cost is not shown.
Cause
The Project Variance by Project Structure report shows the Baseline Cost only for Active Baseline it will not show the Baseline Cost for the Obsoleted Baselines.
Resolution
The report is working fine as system designed behavior.