Symptom

It's necessary to change the required date from a curriculum already assigned or the required date from items that aren't in a curriculum or program (free-floating items).

"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."

Environment

SAP SuccessFactors Learning

Resolution

To change the required date from a curriculum, please proceed according the below steps in the Learning Administration side:

  1. Manage User Learning > Edit Required Dates >

1.png

  1. Click "add one or more from list" > Search for the user ID of the user(s) which you would like to update >
  2. Click "Add" to confirm the user selected and then click "Next" >

2.png

  1. It's possible to add one or more curriculum in step 2. Then, click "Next" to add items not in a curriculum or program in step 3. Skip step 2 entirely if you want to add only items not in a curriculum or program in step 3 >

3.png

  1. In the third step, you can add free floating items. After selecting additional items, click in "Add" and then "Next" >
  1. On the fourth step, you'll set the required date as necessary >

 4.png

  1. After the value has been changed, please click "Finish".

See Also

Keywords

curricula, curriculum, item, modify, assignment, date, update, expiry, expiration, expire, required, by, date, edit required dates, option, how, to, assigned , KBA , lmsadminui , LOD-SF-LMS , Learning Management System , LOD-SF-LMS-ADM , System Admin, Global Variables, References , LOD-SF-LMS-ITE , Items , LOD-SF-LMS-CUR , Curricula , How To