Symptom
You want to perform an activity Immediate change but the button Change Immediate is disabled.
Reproducing the Issue
- Go to Business Configuration Work Center.
- Go to Overview view.
- Search by the activity XYZ.
- Select the activity XYZ.
The Change Immediate button is disabled.
Cause
This a designed behavior.
The immediate change option is available only in the production systems and for the project which is in status go-live.
Resolution
In order to proceed with the change , please perform it via change project activity list.
- Go to Business Configuration work center.
- Go to Implementation Projects view.
- Open Activity List for the project XYZ.
- Search by the activity and make the changes.
Keywords
KBA , AP-PRO , Project Processing , How To