Symptom
When the status of a released task is set to "complete" - the float is set to 0 and then the task is part of the critical path in Gantt-Graphic.
Read more...
Environment
Portfolio and Project Management (PPM)
Product
SAP Portfolio and Project Management 5.0 ; SAP Portfolio and Project Management 6.0 ; SAP Portfolio and Project Management 6.1
Keywords
kritischer Pfad, Puffer, abgeschlossen, Aufgabe, Grafiksicht, rot, CL_DPR_SCHEDULING_SERVICES, CALCULATE_DATES, CL_DPR_UI_LOG_GANTT, CONVERT_DETAIL_DATA, TOTAL_FLOAT , KBA , PPM-PRO , Project Management , Problem