SAP Knowledge Base Article - Public

2165684 - Unable To Consume Quantities Delivered through Project Stock Order

Symptom

You have pre-delivered a product to your customer through a Project Stock Order. When you try to consume the delivered quantity from the project, Consume button is greyed out.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Project Management work center.
  2. Navigate to the Projects view.
  3. Search for the relevant project, choose the Edit button and select the option Products.
  4. Navigate to the sub-tab Project Stock Orders and expand the project stock order against which you have to consume pre-delivered stock.
  5. When you select line item with the product you can see that the Consume button is disabled.

Cause

You have changed status of the line item to Completed by selecting Complete button which is available in the Project Stock Orders sub-tab.

Resolution

Once the status of a project stock order is changed to Complete, there is no undo complete option available.  You will have to return the unconsumed quantities at the pre-delivered stock by performing a New Parts Return Notification. The system is working as designed.

Keywords

Project Stock Order, Delivered Quantity, Consume, Pre-delivered , KBA , AP-PRO , Project Processing , How To

Product

SAP BUSINESS BYDESIGN 1708 ; SAP Business ByDesign 1502 ; SAP Business ByDesign 1505 ; SAP Business ByDesign 1508 ; SAP Business ByDesign 1711 ; SAP Business ByDesign 2402 ; SAP Business ByDesign 2405