Symptom
Two schedule lines are created manually for the same sales order item, and full delivery is enabled. However, the ATP check result is not as expected.
Situation 1:
- Available stock: 150
- Schedule line 1 requested quantity: 200
- Schedule line 2 requested quantity: 100
In this case, neither schedule line receives a confirmation.
Situation 2:
- Available stock: 150
- Schedule line 1 requested quantity: 100
- Schedule line 2 requested quantity: 200
In this case, the first schedule line is confirmed with quantity 100, while the second schedule line remains unconfirmed.
Read more...
Environment
- Sales And Distribution (SD)
- SAP R/3
- SAP ERP
- SAP S/4HANA
- Availability check
- Advanced ATP (aATP)
Product
Keywords
Availability check, schedule line, item, quantity, ATP, Einteilung, Kundenauftrag, Verfügbarkeitsprüfung, Position, OVZJ, RESMD, RESMOD, AVAILABILITY_CHECK_CONTROLLER , KBA , SD-BF-AC , Availability Check , CA-ATP , Available to Promise (ATP) , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.
SAP Knowledge Base Article - Preview