2173156 - ATP Check for Multiple Manually Created Schedule Lines

Symptom

Two schedule lines are created manually for the same sales order item, and full delivery is enabled. However, the ATP check result is not as expected.

Situation 1:

  • Available stock: 150
  • Schedule line 1 requested quantity: 200
  • Schedule line 2 requested quantity: 100

In this case, neither schedule line receives a confirmation.

Situation 2:

  • Available stock: 150
  • Schedule line 1 requested quantity: 100
  • Schedule line 2 requested quantity: 200

In this case, the first schedule line is confirmed with quantity 100, while the second schedule line remains unconfirmed.


Read more...

Environment

  • Sales And Distribution (SD)
  • SAP R/3
  • SAP ERP
  • SAP S/4HANA 
  • Availability check
  • Advanced ATP (aATP)

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

Availability check, schedule line, item, quantity, ATP, Einteilung, Kundenauftrag, Verfügbarkeitsprüfung, Position, OVZJ, RESMD, RESMOD, AVAILABILITY_CHECK_CONTROLLER , KBA , SD-BF-AC , Availability Check , CA-ATP , Available to Promise (ATP) , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.