Symptom
You are defining the tasks of a project. During this process you have created a Milestone as a successor of one of the tasks
The system however scheduled this Milestone to start one day after the predecessor task is finished. Your expectation is that the Milestone should occur on the same day as the task is finished, since you define a lag time of Zero days, however this is not occurring.