SAP Knowledge Base Article - Public

2202131 - Milestone Status Not Permitted; Task XY Is Not Marked As Milestone

Symptom

While migrating a projects you will get above error message.

Reproducing the Issue

  1. Go to Business Configuration work center.
  2. Navigate to Implementation Projects view.
  3. Select the relevant Project and choose the button Open Activity List.
  4. Select Integrate and Extend tab and search for the activity Migration of projects.
  5. Select the activity and choose Open button.
  6. Select the link Migrate projects using the migration tool.
  7. In migrate projects screen select the relevant file and choose Execute Migration button.
  8. System will display above mentioned error messages.

Cause

In the File under the Task Details

If the Project Task is defined as Milestone then Milestone Status should be set as status Not reached (In Planning) / reached (Released), else Project Task is not defined as Milestone then the Milestone Status should be set as status Not Relevant .  

Resolution

System works as designed.

Keywords

KBA , LOD-CRM , Cloud for Customer , How To

Product

SAP BUSINESS BYDESIGN 1705 ; SAP BUSINESS BYDESIGN 1708 ; SAP Business ByDesign 1502 ; SAP Business ByDesign 1505 ; SAP Business ByDesign 1508 ; SAP Business ByDesign 1511 ; SAP Business ByDesign 1602 ; SAP Business ByDesign 1605 ; SAP Business ByDesign 1702 ; SAP Business ByDesign 1711 ; SAP Business ByDesign 1805 ; SAP Business ByDesign 1808