Symptom

Schedule data uploads through the Mass Data Maintenance Work Center using Scheduled Job option

Reproducing the Issue

You can schedule a Job by following the below steps-

1. Go to the Mass Data Maintenance work center

2. Select Import <(Link)>e.g. <Customers>

3. Select Upload Data from Text file

4. Select Execute Migration

5. Select With Scheduled Job

Resolution

Once you schedule a upload, the Data import run is scheduled for 3:00AM. Since this is the standard time set for all customers, changing this time is not possible.

Once a Job is scheduled you will not be able to cancel this job and this needs to be cancelled from backend.

Keywords

KBA , mass data maintenance , scheduled job , SRD-CC-MIG-DMC , Migration: Tool , How To