Symptom

You are trying to consume a material in a Project Stock Order, but the system is showing the error message: Material not available for consumption in project.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Project Management work center.
  2. Navigate to Project Stock Orders view.
  3. Find and select the relevant Project Stock Order ID.
  4. Choose Edit button.
  5. Select the relevant Line Item and click Consume.
  6. Enter the relevant Details and click OK.
  7. The system returns the error message: Material not available for consumption in project.

Cause

You cannot consume the material in case the Project Stock Order does not contain a Ship-From Location for the item type Pickup / Pre-Delivery.

Resolution

Manually complete the project stock order which does not have Ship-From Location and then create a new Project Stock Order with a Ship-From Location.

See Also

3060979 - Error 'Material not available for consumption in project' While Trying To Consume Pre-Delivered Project Stock Order.

2570154 - Error Message :Material Not Available For Consumption In Project

3033616 - Material Not Available For Consumption in Project

3232950 - Material not available for consumption in project

Keywords

Ship-To, Ship-From, Location, Project Stock ID , KBA , AP-PRO , Project Processing , How To

Product

SAP Business ByDesign all versions