Symptom
1/ If customer integrate a BizX instance with an LMS validated instance, how long will BizX instance get upgraded? Quarterly or yearly?
2/ According to the System Requirements(Q4 2015 release), it says "Support for Internet Explorer 8 will be dropped with SAP SuccessFactors Q1 2016 release because Microsoft plans to end support for this browser on January 12, 2016."
Can LMS-Validated system be supported for IE8 until b1608 is released or IE8 is supported only until January 12, 2016?
Environment
Integrated BizX and LMS Validated Instance
Resolution
1/
Bizx—once a quarter and LMS once a year.
2/
End support untill January 12, 2016 because Microsoft will end support for IE8 untill that time.