Symptom
- To Run a Report For E-Verify Activities
Environment
- Applicable for all DC centres and KMS(Zerolag) Customers
- Onboarding / Reports
Resolution
- Below it the Reports work queue. To run a report for E-Verify activities go to Process and select E-Verify from the drop down list.
- From the Activity drop down list you will see several selects. For this example, we will use Initial Verification. Please note if you want to run a report for all E-Verify activities, you must select each ‘Activity’, one at a time and create a report for each activity. You may export the results in an excel. Once you have run all of the reports, you may merge them.
- Select a date range. (If you do not select a date range, you will get all activities in the E-Verify process and in the activity status of initial verification.) Click on Outstanding Activities and then submit. The activities in the Initial verification step will present in the work queue
- You may export to an excel by clicking the excel icon in the work queue. When the message box present, you will click the OK button
Keywords
- E-Verify
- Reports
Product
SAP SuccessFactors Onboarding all versions