2281413 - Copy-Paste of a task with role/resource assignment

Symptom

A task which has a role/resource assignment is copied to a new one within the project in Project Management. The new task doesn´t receive the role/resource assignment of the source task.


Read more...

Environment

  • SAP Portfolio and Project Management (PPM) 6.1
  • SAP Portfolio and Project Management for SAP S/4HANA (EPPM)
  • SAP Portfolio and Project Management in SAP S/4HANA (PPM)

Product

SAP Portfolio and Project Management 6.1 ; SAP Portfolio and Project Management for SAP S/4HANA all versions ; SAP S/4HANA all versions

Keywords

kopieren, einfügen, Rolle, Ressource, Zuordnung, Rollenzuordnung, Ressourcenzuordnung, Besetzung, staffing, BAdI,
CL_DPR_APPL_OBJECT_FACTORY, method IF_DPR_APPL_OBJECT_FACTORY_INT~COPY_TASK,
CL_DPR_TASK_O, method SET_DEFAULTS_UPON_COPYING,
CL_DPR_TASK, method COPY, include task, role assignments to current task , KBA , PPM-PRO , Project Management , Problem