2286957 - "Update Role According to Tasks" does not update role dates

Symptom

A task is assigned to a project role. After changing the time frame of the task you press button "Update Role according to Tasks" in the role. The role dates are not updated in accordance with the task's new time frame.


Read more...

Environment

SAP Portfolio and Project Management (PPM)

Product

SAP Portfolio and Project Management all versions

Keywords

button "Update Role According to Tasks", role dates, project role, task, possible time frame, start date, finish date, task assignment, assigned task, intersection

, KBA , PPM-PRO , Project Management , Problem