You are Time Administrator and would like to know, how the Quantity and Hours field works?
Environment
SAP Business ByDesign
Resolution
Case 1:
-> Enter Start Time and End Time
-> Release
-> Quantity field auto-calculate and display the value
Note:
This quantity is valuated with all the rules for the time type (example: breaks)
Case 2:
-> Enter Start Time and End Time
-> Release
-> Quantity field auto-calculate and display the value
-> Enter Hours
-> save / release
-> Value entered in the hours will be visible in Quantity field. overwritted. This will not validate the rules and the value entered in the hours should be less than or equal to difference b/w start and end time
Keywords
Quantity, Hours, Employee Times Working , KBA , LOD-CRM-EMP , Employee , How To