Symptom
A purchase order (PO) was created against the contract, and a further change is done on contract afterwards. Due to this change, the release of the contract is reset.
When you now try to change the existing PO which references the contract, the system issues error ME 347 (Release orders against contract & not possible (contract not released)). It is not possible to change the PO while the contract is not released.
However, it is possible to release the PO e.g. in ME29N even if the contract is not released at that time.
Read more...
Environment
- Materials Management (MM)
- SAP ERP Central Component
- SAP ERP
- SAP enhancement package for SAP ERP
- SAP enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA
Product
Keywords
MMRSTD, ME 347, contract, release, PO, purchase order, reference, reset, change, higher, release strategy, 06042, 06078, target value, target quantity,
release status, BAdI, ME_PROCESS_PO_CUST, hold status, contract number, document date, vendor, purchasing organization, ME22N. ME347 , KBA , MM-PUR-PO , Purchase Orders , MM-PUR-OA-CON , Contract , MM-PUR-GF-REL , Release (Approval) , Problem