Symptom

  • You maintained a Time Buffer for a given Resource in /SAPAPO/RES01, and would like to consider it:

    1. During scheduling activities of a single order which are linked by an Activity Relationship

      or

    2. During scheduling activities of different orders, which are linked by a Fixed or Dynamic Pegging relationship


Read more...

Environment

  • SAP Supply Chain Managment Production Planning and Detailed Scheduling (SCM-APO-PPS)

Product

SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

Resource-Dependent Time Buffer, Time Relationships, BUFFERTIME, /SAPAPO/CRES_BUFFERTIME_DISP, USE_BUFTIME_RES_PEG, USE_BUFTIME_CONSTR, USE_FIX_PEG, USE_DYN_PEG , KBA , time buffer not considered in ppds , time buffer for resource , scheduling with time buffer , scheduling with time buffers , buffertime not taken into account , SCM-APO-PPS-SCF , Scheduling Functions , SCM-APO-PPS , Production Planning and Detailed Scheduling , SCM-APO-MD-RE , Resource , How To